ISLES of CAPRI WATER SYSTEM

This blog will follow daily the progress of the installation of our new water pipes. The company will be working 4-10 hour days with friday open for surveying and cleaning up on the previous weeks work. The company and the county request that all people that are watching the progress to maintain a safe distance from working personal and equiptment. This blog hopefully will show you the progress daily in order to keep you as informed as possible.













My Blog List

Blog Archive

Thursday, May 27, 2010

PANAY AVE

THE CREW ENDED THE WEEKS WORK TODAY AT PANAY AVE. THEY ENCOUNTERED THIER FIRST CONCRETE DRIVEWAY.

AS SEEN BELOW, PANAY AVE, AS ALL OTHER SIDE STREETS, ARE FED WITH A 2" PIPE, THE NEW PIPE WILL BE 6".

A 3/4" PIPE IS ATTACHED TO THE OLD PIPE TO FEED A WATER TEST STATION AT PANAY.


"DERECK MOORLEY" THE PROJECT MANAGER FOR DN HIGGINS WAS INSPECTING THE WORK TODAY.

THE CREW WILL ENCOUNTER THE FIRST OBSTACLE NEXT WEEK, WHEN THEY HAVE TO REMOVE 2 SETS OF HEDGES. THE FIRST IS THE END OF A HEDGE AND THE SECOND IS A ROW OF HEDGES.