ISLES of CAPRI WATER SYSTEM

This blog will follow daily the progress of the installation of our new water pipes. The company will be working 4-10 hour days with friday open for surveying and cleaning up on the previous weeks work. The company and the county request that all people that are watching the progress to maintain a safe distance from working personal and equiptment. This blog hopefully will show you the progress daily in order to keep you as informed as possible.













My Blog List

Blog Archive

Wednesday, May 26, 2010

SAMAR AVE 6" TAP

EACH STREET HAS AN ISOLATION VALVE AND THE PIPE IS 6" IN DIA. ALSO AT EACH STREET THERE IS A MAIN LINE ISOLATION VALVE (12"). THE PAVEMENT IS CUT OUT, DITCH DUG AND PIPE INSTALLED. THEN THE DITCH IS REFILLED, COMPACTED AND REPAVED.


















FOLLOWING THE DIGGING CREW IS THE CLEAN UP CREW. THEY FILL, REMOVE EXCESS DIRT AND TRASH, AND RAKE AND BROOM IT BACK TO GRADE. 