ISLES of CAPRI WATER SYSTEM

This blog will follow daily the progress of the installation of our new water pipes. The company will be working 4-10 hour days with friday open for surveying and cleaning up on the previous weeks work. The company and the county request that all people that are watching the progress to maintain a safe distance from working personal and equiptment. This blog hopefully will show you the progress daily in order to keep you as informed as possible.













My Blog List

Blog Archive

Tuesday, June 22, 2010

THE LAST HALF OF SAMAR AVE.

THE NEW FIRE HYDRANT THAT IS BEING INSTALLED HALF WAY DOWN SAMAR AVE IS BEING BOLTED TOGETHER.
AN AIR GUN IS USED TO TORQUE THE BOLTS..
MEANWHILE, THE TRACK HOE IS SCRAPING THE GRASS UP AND LOADING IT TO BE CARRIED OFF..
THE CLEAN UP CREW IS SWEEPING THE DRIVEWAY TO PREPARE FOR THE LIME ROCK TO BE LAID AND COMPACTED.



THE BORING CREW IS WORKING ON SAN JUAN AVE. THEY ARE BORING UNDER DRIVEWAYS.

No comments: