EVERY THURSDAY ALL COMPANY AND COUNTY PROJECT MANAGERS, FIELD INSPECTORS AND SUPERINTENDENTS MEET TO DISCUSS THE WEEKS WORK. AT THIS TIME CHANGES THAT COULD OR SHOULD BE MADE ARE PRESENTED AND DISCUSSED. THE PROJECT MANAGER FOR THE COUNTY IS "DIANA DUERI" AND THE SENIOR FIELD INSPECTOR IS "FRED SEXTON"
AT THIS WEEKS MEETING, ONE OF THE ITEMS TO BE DISCUSSED WAS THE MOVING OF THE NEW WATER PIPE TO PREVENT THE REMOVAL OF THE ARECAS ALONG CAPRI BLVD. AT CRISTOBAL ST. DETAILS WILL BE ON A LATER BLOG.
AS THE WORK PASSED LUZON AVE. AND PROCEEDED TO GRENADA AVE, A ROW OF HEDGES WERE REMOVED AND MOVED TO THE LOT ON GRENADA AVE.
THE WARNING SIGNS WERE MOVED, THE GRASS WAS SCRAPPED WHERE THE DITCH WAS BEING DUG, THE CLEAN UP CREW WAS FOLLOWING AND THE WORK PROCEEDED.
APPROACHING GRENADA AVE, THE TELEPHONE LINE AND THE EXISTING WATER PIPE WERE 6" ON EITHER SIDE OF THE NEW WATER PIPE.
THE TELEPHONE COMPANY HAD TO DIG UP AND
MOVE THE LINE, PAST GRENADA AVE. AND THEY WILL BE
INSTALLING A NEW TELEPHONE LINE LATER.
A FITTER PIPE IS USED TO CHECK THE WATER PIPE FOR ROUNDNESS BEFORE INSTALLATION..