This blog will follow daily the progress of the installation of our new water pipes. The company will be working 4-10 hour days with friday open for surveying and cleaning up on the previous weeks work. The company and the county request that all people that are watching the progress to maintain a safe distance from working personal and equiptment. This blog hopefully will show you the progress daily in order to keep you as informed as possible.













My Blog List

Blog Archive

Thursday, June 3, 2010

WEEKLY CONSTRUCTION MEETING

    EVERY THURSDAY ALL COMPANY AND COUNTY PROJECT MANAGERS, FIELD INSPECTORS AND SUPERINTENDENTS MEET TO DISCUSS THE WEEKS WORK. AT THIS TIME CHANGES THAT COULD OR SHOULD BE MADE ARE PRESENTED AND DISCUSSED. THE PROJECT MANAGER FOR THE COUNTY IS "DIANA DUERI" AND THE SENIOR FIELD INSPECTOR IS "FRED SEXTON"

AT THIS WEEKS MEETING, ONE OF THE ITEMS TO BE DISCUSSED WAS THE MOVING OF THE NEW WATER PIPE TO PREVENT THE REMOVAL OF THE ARECAS ALONG CAPRI BLVD. AT CRISTOBAL ST.  DETAILS WILL BE ON A LATER BLOG.


AS THE WORK PASSED LUZON AVE. AND PROCEEDED TO GRENADA AVE, A ROW OF HEDGES WERE REMOVED AND MOVED TO THE LOT ON GRENADA AVE.






THE WARNING SIGNS WERE MOVED, THE GRASS WAS SCRAPPED WHERE THE DITCH WAS BEING DUG, THE CLEAN UP CREW WAS FOLLOWING AND THE WORK PROCEEDED.




APPROACHING GRENADA AVE, THE TELEPHONE LINE AND THE EXISTING WATER PIPE WERE 6" ON EITHER SIDE OF THE NEW WATER PIPE.


THE TELEPHONE COMPANY HAD TO DIG UP AND
MOVE THE LINE, PAST GRENADA AVE. AND THEY WILL BE
INSTALLING A NEW TELEPHONE  LINE LATER.

A FITTER PIPE IS USED TO CHECK THE WATER PIPE FOR ROUNDNESS BEFORE INSTALLATION..