ISLES of CAPRI WATER SYSTEM

This blog will follow daily the progress of the installation of our new water pipes. The company will be working 4-10 hour days with friday open for surveying and cleaning up on the previous weeks work. The company and the county request that all people that are watching the progress to maintain a safe distance from working personal and equiptment. This blog hopefully will show you the progress daily in order to keep you as informed as possible.













My Blog List

Blog Archive

Wednesday, July 14, 2010

DAY 2 BACTERIA TEST - WATER MAIN

JENNIFER HUBBARD, FROM THE COLLIER COUNTY LAB, TOOK THE DAY 2 TESTS AT THE 11 TEST POINTS.
THE FIRST SAMPLE POINT IS AT THE WATER PLANT TO GET A BACKGROUND LEVEL..

THE TELEPHONE CABLE CREW IS BORING A LINE ACROSS THE PARKING LOT AT PELICAN BEND RESTAURANT.. 
THE SPLICING CREWS ARE CONNECTING THE BUSINESS'S TO THE NEW TELEPHONE LINE..

THE DIGGING CREW IS CONTINUING TO CHRISTOPHER REALITY AND A TURN IN THE NEW WATER PIPE..
THE COUNTY AND THE DIGGING CREW WANTS TO REMIND DRIVERS TO BE SAFE..
THEY ARE WORKING CLOSE TO THE ROAD AND NEED OUR HELP TO KEEP EVERYONE SAFE..