ISLES of CAPRI WATER SYSTEM

This blog will follow daily the progress of the installation of our new water pipes. The company will be working 4-10 hour days with friday open for surveying and cleaning up on the previous weeks work. The company and the county request that all people that are watching the progress to maintain a safe distance from working personal and equiptment. This blog hopefully will show you the progress daily in order to keep you as informed as possible.













My Blog List

Blog Archive

Thursday, July 1, 2010

FLUSHING DAY FROM ANTIGUA ST. TO SAN JUAN AVE.-CONCRETE

   THE 12" NEW WATER MAIN IS CONNECTED TO THE 12" MAIN WATER VALVE AT THE WATER PLANT.
    ( SEE MAY 19TH BLOG FOR MORE INFO )
THE FLUSH BEGINS AT THE FIRST CURVE..
( PHOTOGRAPH BY DERECK MOORLEY, PROJECT MANAGER OF DN HIGGINS)

AT EACH STREET THE SUB-MAIN IS OPENED AND "DAVE LATERNEAU", COUNTY INSPECTOR, TEST THE WATER AT THE WATER CANON UNTIL THE SEDIMENT IS CLEARED.
THEY START AT LUZON AVE.
THEN PROCEED TO GRENADA AVE.
SUPERVISING ALONG THE WAY ARE THE SENIOR FIELD INSPECTOR " FRED SEXTON" AND THE PROJECT MANAGER "DIANA DUERI"
NEXT IS PANAY AVE..
AND THE SEDIMENT TEST CONTINUES..
THEN SAMAR AVE.
ALONG THE WAY ALL OF THE FIRE HYDRANTS ARE FLUSHED
THEN SAN JUAN AVE. IS LAST..
AND THE FINAL SEDIMENT TEST ARE TAKEN..
ALL OF THE INSPECTORS ARE SATISFIED THAT THE WATER IS CLEAR OF SEDIMENT..


DURING THIS TIME THE CONCRETE CREW IS POURING ON PANAY AVE. AND FINISHING THE DRIVEWAYS OFF.