ALL OF THE NEW HYDRANTS THAT DO NOT HAVE A BAG OVER THEM, ARE NOW IN SERVICE. FOR NOW THE OLD HYDRANTS WILL BE IN SERVICE ALSO.
THE DIGGING CREW IS STARTING ON PANAY AVE AND WORKING TOWARD SAN JUAN AVE. THEY ARE RUNNING THE BLUE NEW WATER PIPE TO THE METER AREA.
THE SADDLE TAPS THAT WILL FIT AROUND THE 6" NEW WATER PIPE ARE LAID OUT..
THE DITCHES TO THE METERS ARE HAND DUG..
A SINGLE BLUE WATER PIPE WILL SPLIT TO FEED TWO METERS..
THE SADDLE TAPS ARE INSTALLED ON THE 6" NEW WATER PIPE..
THE PIPE IS DRILLED, USING THE NEW TAP ..
THE BLUE PIPE IS SLIPPED THROUGH THE SLEEVE THAT IS UNDER THE ROAD..
AND CONNECTED TO THE SADDLE TAPS..
THE VALVES ARE OPENED AND THE LINES FLUSHED..
THEN COVER, CLEAN THE AREA AND ON TO THE NEXT WATER SERVICE.