THESE FOUR TAPS WILL FEED 6 NEW WATER METERS, 2 ON EACH SIDE OF THE ROAD AND 2 ON THE CUL-DE-SAC.
AND WHEN ALL IS DONE THE PIPES ARE FLUSHED OUT..
ANOTHER PART OF THE CREW IS INSTALLING CONCRETE CURBS AROUND ACCESS HOLES FOR THE ISOLATION VALVES..
AND THE NIGHT CREW IS GETTING THE PIPE READY TO BE CUT IN TONIGHT AT THE FIRE HOUSE.
THEY HAVE CONNECTED THE 6" VALVE AND ARE INSTALLING THE SADDLES ON EACH SIDE OF THE VALVE..
THE SPECIAL DRILL IS USED TO CUT THE TAP IN THE SADDLE..
THESE 2 TAPS WILL ALLOW THE FLUSHING OF THE WATER PIPE AFTER THE WORK IS COMPLETED..
THE INSTALLATION OF THIS VALVE WILL PERMIT THE DIGGING CREW TO HOOK UP THE TEMPORARY WATER PIPE ACROSS THE BRIDGE..
THE NIGHT LIGHTS ARE IN PLACE FOR THE WORK TONIGHT..
AFTER A 4 DAY HOLIDAY WEEKEND, WHERE EVER YOU LOOK, EVERY BODY AND EVERY THING HAS A SMILE.