ISLES of CAPRI WATER SYSTEM

This blog will follow daily the progress of the installation of our new water pipes. The company will be working 4-10 hour days with friday open for surveying and cleaning up on the previous weeks work. The company and the county request that all people that are watching the progress to maintain a safe distance from working personal and equiptment. This blog hopefully will show you the progress daily in order to keep you as informed as possible.













My Blog List

Blog Archive

Thursday, October 28, 2010

NEW WATER CONNECTIONS - BACK FLOW PREVENTER TEST

DIANA DUERI, "PROJECT MANAGER",  INSPECTED THE WORK AREAS TODAY WITH JERRY ZIMMERMAN "FIELD INSPECTOR".

THE CREW STARTED CONNECTING THE NEW WATER METERS AT TRULUCKS FISH HOUSE..


THEN MOVED TO THE ISLAND MARKET..


FIELD INSPECTOR "JERRY AND WATER METER INSTALLER "BRUCE" EXPLAIN TO ME WHY THE MIDWEST BACK FLOW PREVENTER TEST KIT IS USED BEFORE THE WATER IS TURNED ON..



FIRST, THE AIR IS BLED OFF..


THEN THE TEST KIT IS CONNECTED ACROSS THE FIRST CHECK VALVE AND THE SPRING PRESSURE IS MEASURED TO INSURE THAT IT WILL SEAT PROPERLY..


THEN THE OTHER CHECK VALVE AND THE BLEED OFF VALVE'S SPRING PRESSURE IS TESTED. IF THE TEST FAILS , THE VALVES ARE DISMANTLED AND CLEANED. WHEN THE TEST IS GOOD, THE WATER IS TURNED ON TO THE CUSTOMER..


THE SLEEVE INSTALLED AT GEM REMOTES IS UNCOVERED  TO ALLOW FOR THE NEW 1 1/2" BLUE WATER PIPE TO BE SLIPPED THROUGH..



THE DITCH IS OPENED..


AND THE SIDE WALK IS CUT..


THE CREW THEN MOVES TO THE HOMES ACROSS THE STREET FROM CRISTOBAL ST AND ANTIGUA AVE.  THEY OPEN THE DITCH TO CONNECT TO THE NEW WATER PIPE AND SLIP THE NEW PIPE THROUGH THE SLEEVE..