This blog will follow daily the progress of the installation of our new water pipes. The company will be working 4-10 hour days with friday open for surveying and cleaning up on the previous weeks work. The company and the county request that all people that are watching the progress to maintain a safe distance from working personal and equiptment. This blog hopefully will show you the progress daily in order to keep you as informed as possible.













My Blog List

Blog Archive

Thursday, October 28, 2010

NEW WATER CONNECTIONS CONTINUE

"BRUCE" WITH THE COLLIER COUNTY WATER DEPARTMENT, ASSEMBLES THE BACK FLOW PREVENTER FOR THE CREW TO INSTALL..

NEW METERS ARE INSTALLED AT CHRISTOPHER REALITY, THE BLUE HERON..


AND THE HOMES ACROSS FROM CRISTOBAL ST..


THE NEW WATER PIPE IS RAN THROUGH AN EXISTING SLEEVE THAT IS UNDER CAPRI BLVD..


THE DITCH IS HAND DUG FROM THE ROAD TO THE WATER METERS..


A "Y" IS INSTALLED TO FEED 2 METERS..


AND THE PIPE IS FLUSHED BEFORE CONNECTING THE NEW METERS..


AFTER THE METER, THE BACK FLOW PREVENTER IS INSTALLED..


THE BORING COMPANY IS CROSSING CAPRI BLVD AT GEM REMOTES..