THE CREW IS TAKING A 4 DAY WEEKEND FOR THE HOLIDAY. THEY WILL FINNISH THIS WEEK PULLING THE 8" OLD WATER PIPE OUT OF THE GROUND FROM ANTIGUA ST TO THE WATER STATION.
FIRST, THEY ARE REMOVING THE 6" WATER PIPE CONNECTION AT THE WATER STATION..
THE 6" MAIN ISOLATION VALVE IS EXPOSED AND THE OUTPUT PIPE IS REMOVED. THERE WILL BE CONCRETE POURED AT THIS AREA TO KEEP THE VALVE FROM BLOWING OUT AND ALLOW FOR THE GROUT TO BE PUMPED INTO THE 6" OLD WATER PIPE..