THE GROUTING OF THE REMAINING OLD WATER PIPES FROM THE BRIDGE TO THE WATER STATION WAS COMPLETED TODAY. A CONCRETE PUMP IS KEPT FULL OF GROUT, USING A CONCRETE TRUCK..
TRAFFIC IS REDUCED TO ONE LANE..
THE CONCRETE PUMP IS ATTACHED TO THE UNDERGROUND PIPE..
THE GROUT IS PUMPED INTO THE PIPE UNDER HI PRESSURE..
THE EXISTING WATER IS PUSHED OUT AS THE GROUT IS PUMPED IN..
WHEN THE GROUT COMES OUT, THE PUMPING IS STOPPED..
THE PUMP IS MOVED ON TO THE NEXT PLACE..
AND AGAIN, THE WATER IS PUSHED OUT, AS THE GROUT ENTERS..
AND THE GROUT IS STOPPED WHEN THE PIPE IS FULL..
THE THURSDAY PROGRESS MEETING WAS HELD AT THE FIRE HOUSE. DISCUSSED WAS THE PAVING, WHICH SHOULD START ABOUT DECEMBER 13TH, AND WILL START AT THE FIRE HOUSE AND MOVE NORTH, TO ACCOMMODATE THE WEDDING PLANNED FOR THE 18TH AT PELICAN BEND. THE WATERING OF THE NEW GRASS WILL BE UNTIL IT TAKES ROOT AND HOMEOWNERS WILL HAVE TO TAKE RESPONSIBILITY OF THEIR RIGHT OF WAY GRASS.