THE TRAFFIC IS FLOWING IN A SAFE MANNER AS THE DIGGING CREW IS WORKING ACROSS FROM THE COMMUNITY CENTER..
AS THE DIGGING CREW IS APPROACHING THE CURVE AT ISLAND MARKET, A 6" SUB-MAIN TAP IS INSTALLED TO FEED TARPON VILLAGE AND THE FISH HOUSE..
THE NEXT TURN IS A 45* ANGLE AND HAS TO CROSS BOTH EXISTING WATER PIPES AND THE FIBER OPTIC LINE..
THE 8" EXISTING WATER LINE IS EXPOSED AT A PLACE WHERE IT IS COUPLED, A METAL BRACE IS ADDED TO KEEP IT FROM BEING DAMAGED..

NEXT, THE 6" EXISTING WATER LINE IS UNCOVERED AND AN UNMARKED WATER TAP THAT HAS ROTTED FALLS OFF CAUSING A WATER LEAK. THE WATER PRESSURE IS LOWERED ON THE ISLAND AND A METAL SLEEVE IS INSTALLED OVER THE TAP TO ISOLATE THE LEAK..
THE CREW CONTINUED TO DIG AND UNCOVER THE FIBER OPTICS AND TELEPHONE LINES..
THE TELEPHONE DIGGING CREW IS FINISHED FOR NOW..
AND CENTURY LINK IS CONTINUING TO CONNECT THE BUSINESSES TO THE NEW LINE IN ORDER TO ABANDON THE OLD LINES.