THE CREW IS LAYING THE NEW GRASS, STARTING AT THE BRIDGE AND WORKING NORTH.
THEY ARE ALSO CLEANING OUT THE STORAGE YARD..
AND HAULING OFF THE MATERIAL..
THE REMOVAL OF THE OLD 10" PVC CONTINUES. FROM PANAY TO THE PARK AREA, THE 10" WILL BE FILLED WITH GROUT TO PREVENT THE REMOVAL OF THE ROAD AND TWO DRIVEWAYS..
THE REMOVAL CONTINUES UP CAPRI BLVD..
AS THE PIPE IS PULLED FROM THE GROUND, ANOTHER CREW MEMBER FILLS THE DITCH..
IT IS DISCOVERED THAT THE OLD PIPE RUNS DIRECTLY BENEATH THE MEMORIAL FOR "JOAN KREITZER"..
THE SUPERINTENDENT AND COUNTY INSPECTOR DECIDED TO STOP THE REMOVAL OF THE PIPE AND RE-CONTINUE THE DIGGING ON THE OTHER SIDE OF THE TREE..
THIS PREVENTED THE REMOVAL OF THE TREE AND DISTURBING THE GROUND AND ROOTS..
THANK YOU DN HIGGINS CO.
THANK YOU COLLIER COUNTY
THE CREW CONTINUED TOWARD THE ENTRANCE SIGN..
THE PIPE RAN PARALLEL TO CAPRI BLVD..
THE DIGGING PASSED THE ENTRANCE SIGN WITH OUT ANY DISTURBANCE..
ALL OF THE OLD PIPE IS REMOVED TO THE STORAGE AREA AND PREPARED FOR HAULING TO THE DUMP..
FELIPE AND ESTEBAN, WITH DN HIGGINS CO, FOLLOW THE COVERING OF THE OLD PIPE BY DOING A FINAL GRADING AND RAKING OF THE AREA TO PREPARE IT FOR THE NEW GRASS..
THE GRASS IS CUT IN A STRAIGHT LINE AND ALL DEBRIS IS PICKED UP..
AND HAULED AWAY..
THE NEW GRASS ARRIVES AT THE BRIDGE..
AND IS UNLOADED..
THE GRASS LAYING CREW LAYS THE NEW GRASS STARTING AT THE BRIDGE AND GOING NORTH..
THIS IS WHERE PHASE TWO IS STARTING..
THE GRASS IS DISTRIBUTED TO THE LOCAL AREAS AND LAID IN PLACE..
NOTE:
THE SUPERINTENDENT IS ASKING EVERY ONE NOT TO PARK ON THE GRASS ACROSS FROM THE CIVIC ASSOC. IT WILL TAKE SOME TIME FOR THE NEW GRASS TO TAKE ROOT. HE IS ASKING ALL TO BE PATIENT AND TO NOT CROSS THE BARRIER..