THE DIGGING CREW STARTED AT THE FIRST CURVE TO RUN THE 6" NEW WATER LINE TO ANTIGUA ST. THEY WERE WORKING NEXT TO THE ROAD WITH CONCRETE BARRIERS AND A FLAGMAN TO PROTECT THEM. "JIM NELSON", THE SUPERINTENDENT OF THE CREW, ASKED ME TO NOTE ON THIS BLOG THAT CARS WERE SPEEDING AND COMING CLOSE TO THE CREW. HE HAS ASKED ALL OF US TO PLEASE SLOW DOWN AND WATCH THE FLAGMEN WHEN DRIVING THROUGH THESE CONSTRUCTION AREAS.
(the car in this picture was not an offender, it was just used for the photograph)
THE CREW HAS MADE IT AROUND THE CORNER AND ONTO ANTIGUA ST.
THE CONCRETE CREW HAS FORMED AROUND THE FIRE HYDRANTS AND IN GROUND WATER VALVES. IT IS REQUIRED TO HAVE A 24"SQUARE AND 6"DEEP SLAB WITH REBAR.
THE DRIVE WAYS ARE BEING FORMED TO 6" DEEP WITH EXPANSION JOINTS.