ISLES of CAPRI WATER SYSTEM

This blog will follow daily the progress of the installation of our new water pipes. The company will be working 4-10 hour days with friday open for surveying and cleaning up on the previous weeks work. The company and the county request that all people that are watching the progress to maintain a safe distance from working personal and equiptment. This blog hopefully will show you the progress daily in order to keep you as informed as possible.













My Blog List

Blog Archive

Wednesday, June 30, 2010

BEES, NEW CONCRETE AND ANTIGUA ST.

WITH IN 5 DAYS ANOTHER BEE ATTACK HAS HAPPENED. THIS TIME IT WAS A HOME OWNER MOWING OVER A WATER METER AND HE TRIED TO SPRAY THEM AND THE SPRAY STIRRED UP THE NEST.  THEY WERE AS AGGRESSIVE AS THE FIRST BEES WERE. SINCE THE WATER METERS ARE READ BY A REMOTE DEVICE, THEY ARE VERY RARELY OPENED. ISLES OF CAPRI FIRE CHIEF "ROD RODRIGUEZ". STATED THAT THEY SHOULD NOT BE SPRAYED,  BUT CALL THE FIRE HOUSE IF YOU ARE ATTACKED. (394 3206)  THE FIRE DEPARTMENT HAS THE CORRECT SOLUTION TO KILL THEM.
THE FIRST BEE ATTACK AREA WAS OPENED. IT WAS FOUND THAT THE ENTIRE INSIDE OF THE TELEPHONE BOX WAS FULL OF HIVES. IT WILL BE REPLACED WITH A NEW FIBERGLASS BOX THAT IS SEALED.


THE CONCRETE CREW POURED AND FINISHED OFF THE DRIVEWAYS ON LUZON AVE. THEY ARE RAISING THE DRIVEWAY LEVEL ABOUT 1". THIS IS TO MATCH THE NEW ASPHALT THAT WILL BE LAID WHEN THE PROJECT IS FINISHED.
THE WATER VALVES AND FIRE HYDRANT ALSO HAD A CONCRETE PAD POURED AROUND THEM..
THE CONCRETE CREW DUG OUT AND FORMED THE DRIVEWAYS ON PANAY AVE.


THE DIGGING CREW IS FINISHING ANTIGUA ST. THEY HAVE TO CUT ASPHALT TO COMPLETE THE RUN
THE GRASS IS SCRAPED UP..
THE NEW 6" WATER PIPE IS COUPLED TO THE PIPE THAT IS BORED UNDER A DRIVEWAY..
THE RAINS CAME AROUND NOON..
AND WHEN THEY WERE OVER THE CREW
CONTINUED TO LAY THE NEW PIPE

AND CLEAN UP AS THEY GO
THE CANON FLUSH DEVICE IS READY TO FLUSH OUT THE SYSTEM