ISLES of CAPRI WATER SYSTEM

This blog will follow daily the progress of the installation of our new water pipes. The company will be working 4-10 hour days with friday open for surveying and cleaning up on the previous weeks work. The company and the county request that all people that are watching the progress to maintain a safe distance from working personal and equiptment. This blog hopefully will show you the progress daily in order to keep you as informed as possible.













My Blog List

Blog Archive

Thursday, August 12, 2010

MEETINGS - CRISTOBAL

TWO MEETINGS HAPPENED TODAY, THE FIRST MEETING WAS A SAFETY MEETING WITH THE CREW OF DN HIGGINS.  THE PROJECT MANAGER "DERECK MOORLEY" CONDUCTED THE MEETING AT THE WORK SITE ON CRISTOBAL. TALKED ABOUT WAS A REMINDER OF ALL OF THE SAFETY RULES AND PROCEDURES  THAT ARE BEING USED DURING THE INSTALLATION OF OUR NEW WATER SYSTEM.  ALSO DISCUSSED WAS THE POSSIBLE HAZARDS THAT COULD BE ENCOUNTERED.




THE SECOND MEETING WAS THE WEEKLY CONSTRUCTION MEETING. DISCUSSED WAS THE NEW WATER CONNECTIONS THAT WILL BE HAPPENING VERY SOON, STARTING ON ANTIGUA ST. ALSO DISCUSSED WAS THE CLEAN UP IN FRONT OF BUSINESSES AND THE SWALES.


ON CRISTOBAL THE CREW DISCOVERED A 2" PVC EXISTING WATER LINE THAT  WAS UNKNOWN TO ANYONE AND NOT ON ANY PRINT. AS SEEN IN PREVIOUS POSTS, THESE UNMARKED PIPES HAVE BEEN FOUND AND THIS WILL VERY LIKELY  HAPPEN AGAIN..


 


FIRST,  A WATER PUMP IS  PUT INTO THE DITCH TO LOWER THE LEVEL OF THE WATER TO ALLOW THE REPAIR TO PRECEDE..




THE PUMP IS DIRECTED TOWARD A DRAINAGE PIPE..




A WELL IS DUG IN THE DITCH AND GRAVEL IS PLACED OVER THE SUCTION OF THE WATER PUMP..





THE PROJECT MANAGER OF DN HIGGINS AND COUNTY INSPECTOR DISCUSS A SOLUTION..




IT IS DECIDED TO MAKE A SPLICE WITH SLIP COUPLING'S OVER THE 2" EXISTING WATER PIPE..







BECAUSE OF THE WATER PRESSURE KEEPING COUPLING FROM BEING TIGHTENED, THE WATER COMPANY TRIES TO REDUCE THE PRESSURE. THE EXISTING WATER VALVE IS BURIED IN THE ARECA'S AND IS NOT ABLE TO BE TURNED..








THE PROJECT MANAGER FROM COLLIER COUNTY, "DIANA DUERI", EXAMINES THE SITUATION..





ONE OF THE COUNTY WATER OFFICIALS HAS THE IDEA TO INSTALL A SLIP COUPLING ON EACH CUT END OF THE 2" PVC.  THIS COUPLING HAS A SHUT OFF VALVE BUILT IN AND AFTER INSTALLATION THE VALVE IS SHUT OFF. THEN A FLEXIBLE PIECE OF BLUE WATER PIPE IS INSTALLED IN EACH END AND THE TWO VALVES ARE REOPENED..





THE CREW CAN NOW CONNECT THE 6"SUB-MAIN NEW WATER PIPE TO THE WATER PIPE THAT WAS BORED UNDER THE DRIVEWAY AND CONTINUE ON CRISTOBAL ST..






AS ALL OF THIS HAPPENS, CRISTOBAL ST IS KEPT OPEN TO ALL TRAFFIC..




THE DIGGING CREW CONTINUES TO THE END OF THE STREET..



WHEN THE DAY ENDS, AND THE CREW IS FINISHED CLEANING THE DIRT AND SILT FROM THE STREET AND DRIVEWAYS.... IT LOOKS AS IF NOTHING HAD HAPPENED..

No comments: