ISLES of CAPRI WATER SYSTEM

This blog will follow daily the progress of the installation of our new water pipes. The company will be working 4-10 hour days with friday open for surveying and cleaning up on the previous weeks work. The company and the county request that all people that are watching the progress to maintain a safe distance from working personal and equiptment. This blog hopefully will show you the progress daily in order to keep you as informed as possible.













My Blog List

Blog Archive

Friday, October 29, 2010

PHASE TWO PRE-CONSTRUCTION MEETING

THE COLLIER COUNTY PROJECT MANAGER ,"DIANA DUERI" ALONG WITH THE  SENIOR INSPECTOR, FIELD INSPECTOR , CONTRACT SPECIALIST, WATER DEPARTMENT PERSONAL, LAND ACQUISITION PERSONAL, SAFETY SPECIALIST,  WATER QUALITY PERSONAL, CENTURY LINK,  SURVEYERS,  ENGINEER FROM GRADY MINOR AND THE CONTRACTOR FOR PHASE TWO,"HASKINS, INC",  ALL GATHERED TODAY TO DISCUSS THE NEW PHASE TWO PROJECT. 


THE OFFICIAL STARTING TIME IS NOVEMBER 1, 2010 AND THE COMPLETION WILL BE 300 CONSECUTIVE WORK DAYS FROM THAT TIME.
A CONSTRUCTION STORAGE SITE WITHIN THE PHASE TWO AREA IS BEING SEARCHED FOR. A POSSIBLE SITE IS THE LAND BRIDGE BETWEEN ISLAND 1 AND ISLAND 2.
THE WORK HOURS WILL BE FROM 7:00 AM TO 5:00 PM MONDAY THRU THURSDAY WITH FRIDAY USED TO CLEAN UP THE WEEKS WORK AND PREPARE FOR THE NEXT WEEKS WORK.
"JOEL CHAMBERS", THE OPERATIONS MANAGER WITH "HASKINS,INC",  STATED THAT THEIR FIRST PHASE OF WORK WILL BE TO RUN THE NEW 10" WATER PIPE FROM THE BRIDGE TO PELICAN ST.  THIS WATER PIPE IS TO BE INSTALLED ON THE WEST SIDE OF CAPRI BLVD AND SHOULD BE IN BY THE END OF NOVEMBER. THE NEW WATER CONNECTIONS WILL POSSIBLY BEGIN FROM THE SOUTH END OF THE ISLAND AND WORK BACK TO THE NORTH IN ORDER TO KEEP A CONTINUOUS FLOW OF WATER IN THE NEW WATER PIPE FOR QUALITY CONTROL.
AS IN PHASE ONE, ALL SPECIAL DRIVEWAYS WILL HAVE THE NEW WATER PIPE BORED UNDER THEM, POSSIBLY EVEN THE "OCTOPUS" ON TRINIDAD.
IF ANY RESIDENTS HAVE ANY CONCERNS ABOUT THE COMING CONSTRUCTION, YOU MAY LEAVE A COMMENT ON THIS BLOG OR CALL THE PROJECT MANAGER
"DIANA DUERI" AT  252-4218
 EITHER WAY,  YOUR CONCERNS WILL BE ADDRESSED.


No comments: